Steel frame under construction at Springwood Court, Springwood Industrial Estate, Braintree

Current Project — In Progress

Springwood Court, Braintree

A bespoke commercial steel building at Springwood Court, Springwood Industrial Estate, Braintree — designed and modelled in Tekla, fabricated by our team, and now being erected for a commercial development company.

Client
Commercial development company
Location
Braintree, Essex
Status
Frame erection underway
Scope
Design, fabrication, installation

Design First

Modelled in Tekla Before a Beam Was Cut

Springwood Court started on screen, not on site. Using Tekla Structures we built a complete 3D model of the building — the full portal frame, purlins, bracing and every connection — so the client and engineer could see exactly what would be built before committing to fabrication.

  • Accurate 3D model of the full frame and connections
  • Fabrication drawings generated directly from the model
  • Clashes and connection issues resolved before site
  • Every steel member labelled to match its modelled position
Steel rafters and safety netting on the Tekla-designed Springwood Court frame

Progress & Timeline

From Model to Site

  1. 01

    Design & Planning in Tekla

    Complete

    The project began in the model. Working from the client's brief, our team produced a full 3D Tekla Structures model of the portal frame — every column, rafter, purlin, eaves beam and connection detailed before a single piece of steel was ordered.

  2. 02

    Detailing & Approval

    Complete

    General arrangement and fabrication drawings were generated directly from the Tekla model and issued to the client and engineer for approval. Modelling everything first meant clashes and connection issues were resolved on screen, not on site.

  3. 03

    Procurement & Fabrication

    Complete

    With approvals in place, material lists came straight out of the model. The frame was fabricated, cut, drilled, painted and quality checked — every member labelled to match its position in the Tekla model for a fast, accurate erection sequence.

  4. 04

    Steel Erection — On Site Now

    On site now

    The frame is going up at Springwood Court. Columns and rafters are being erected bay by bay with full edge protection and safety netting throughout, keeping the programme on track and the site safe at every stage.

  5. 05

    Cladding & Completion

    Up next

    Insulated roof and wall cladding panels are already delivered and staged on site, ready to follow the frame. Once the envelope is complete we'll hand over a finished, weathertight building to the developer.

On Site

Latest Progress Photos

View along the rafters of the Springwood Court steel frame with safety netting during erectionTelehandler working under the steel frame at Springwood Court, Springwood Industrial Estate, BraintreeInterior of the Springwood Court steel portal frame building under constructionSpringwood Court steel frame from the estate road with cladding panels delivered and ready for installationSteel purlins and roof plane of the Springwood Court building during erectionCladding materials staged inside the Springwood Court steel frame in BraintreeStacks of insulated cladding panels awaiting installation at Springwood CourtRoof safety netting across the Springwood Court portal frame during constructionSite access staircase and scaffold at the Springwood Court project in Braintree